150 extended-length plastic extruder
Equipment Installation
This equipment can be installed on a pre-cast concrete foundation or placed directly on a flat, level surface. The entire unit is equipped with vibration-damping feet.
During installation, ensure proper layout and leave adequate operating space.
Equipment Operating Instructions
Before conducting a trial run, carefully inspect the following items:
1. Verify that the site’s power supply parameters match those specified in this manual and confirm that all electrical components are correctly connected.
2. Check all connections for looseness; if any are loose, tighten them promptly.
3. Confirm that the gearbox contains the correct type of lubricant and that the oil level is sufficient. Use medium‑pressure gear oil N151 or another gear oil of similar viscosity. The oil level should reach the upper mark on the gearbox oil dipstick.
4. Manually rotate the coupling connecting the main motor to the gearbox in a clockwise direction for at least two full revolutions, ensuring smooth and flexible operation.
5. Verify that the main motor rotates in the correct direction: when viewed from the head end, it should turn clockwise.
After completing these checks, proceed with the host machine’s trial run according to the following steps:
1. Increase the host temperature to a level appropriate for the specific material being processed; users may set this value independently. Once the desired temperature is reached, maintain it for 0.5–1 hour. Monitor the temperature control system throughout the heating process to ensure proper functioning.
2. Inspect the cooling water system to confirm it is operating normally and check for leaks; address any issues immediately.
3. After completing the above steps, begin rotating the screw. Do not feed material initially; gradually increase the screw speed to approximately 41 rpm and run the machine idling for about 4–5 minutes. Observe whether the equipment operates smoothly. If any abnormalities occur, stop the machine, troubleshoot the issue, and then restart.
4. Gradually increase both the screw speed and the feed rate until the desired production output is achieved.
Maintenance Instructions
I. Main Motor
1. The deviation between the actual supply voltage and the rated value should not exceed 5%; similarly, the deviation in supply frequency should not exceed 1%.
2. Replace the motor’s grease every 4,000 hours of operation using No. 3 base grease. If the motor remains idle for an extended period, inspect the bearings for grease before reuse and replenish as necessary, filling the bearing housing to approximately two-thirds of its capacity.
3. During operation, if bearing temperatures become excessively high or the grease deteriorates, replace the grease promptly. Normal operating temperatures for bearings should not exceed 95°C.
4. Store the motor in a clean, cool, and dry environment when not in use.
5. Before reusing a long‑idle motor, measure its insulation resistance; it must be no less than 0.5 MΩ. If the reading falls below this threshold, perform drying treatment, ensuring the winding temperature does not exceed 121°C.
II. Gearbox
1. Prior to use, fill the gearbox with lubricant—medium‑pressure gear oil or another gear oil of similar viscosity—until the oil level reaches the marked level on the dipstick. Note: Never operate the gearbox without adequate lubrication.
2. Maintain the gearbox within an ambient temperature range of 1–35°C. If the temperature exceeds this range, install a heating or cooling device as needed.
3. After 300–600 hours of operation, change the lubricant; thereafter, replace it every 4,000 hours. Perform this replacement while the gearbox is stopped and still warm; drain the old lubricant, flush the gearbox thoroughly with fresh lubricant of the same grade, and then refill with the prescribed amount of new lubricant.
4. If the gearbox has been idle for an extended period, run it empty for a short time before loading material to ensure adequate lubrication of the bearings. Regularly inspect all connections and monitor gear wear, addressing any issues promptly.
5. During operation, if abnormal noise, vibration, or overheating occurs, stop the machine immediately, investigate the cause, and resolve the problem before resuming use.
III. Screw Removal Instructions
1. Before removing the screw, first dismantle the extruder head and ensure sufficient working space. Drain as much material as possible from the screw prior to disassembly.
2. Perform screw removal only when the host machine is maintained at its normal operating temperature. Take appropriate precautions to protect personnel from burns, and handle the screw carefully to avoid damage.
Key words:
150 extended-length plastic extruder
Classification:
Plastic extruder
Business Hotline:
150 extended-length plastic extruder
Equipment Installation
This equipment can be installed on a pre-cast concrete foundation or placed directly on a level, stable surface. The entire unit is equipped with vibration‑isolating feet.
During installation, ensure a well-organized layout and leave adequate clearance for operation.
Equipment Operating Instructions
Prior to the equipment’s trial run, the following items shall be inspected one by one.
1. Verify that the on-site power supply parameters match those specified in this manual, and confirm that all electrical components are properly connected.
2. Inspect all connection points for looseness; if any are found, tighten them promptly.
3. Check that the gearbox contains the correct lubricant and that the oil level is adequate. Use medium‑pressure gear oil N151 or another gear oil of similar viscosity; the oil level should reach the upper mark on the gearbox oil dipstick.
4. Manually rotate the coupling connecting the main motor to the gearbox, ensuring it turns clockwise for at least two full revolutions; the rotation must be smooth and free of binding.
5. Verify that the main motor is rotating in the correct direction: when viewed from the head end, it should rotate clockwise.
After completing the inspections of the aforementioned items, a trial run of the host unit may be conducted. The main steps are as follows:
1. Increase the host temperature; the specific setting varies depending on the material and should be determined by the user. Once the host temperature reaches the set value, maintain that temperature for 0.5 to 1 hour. During the heating process, carefully verify that the temperature control is functioning properly.
2. Verify that the cooling water system is functioning properly. Check for leaks and, if any are present, address them promptly.
3. After completing the above steps, you may begin rotating the screw. Do not feed material at this stage; gradually increase the screw speed to approximately 41 r/min and run the machine idling for about 4–5 minutes, observing whether the equipment operates normally. If any abnormalities are detected, stop the machine, troubleshoot the issue, and then restart it.
4. Gradually increase the screw speed and feed rate until the desired production output is achieved.
Maintenance Instructions
I. Main Motor
1. The deviation of the supply voltage from its rated value shall not exceed 5 percent, and the deviation of the supply frequency from its rated value shall not exceed 1 percent.
2. Every 4,000 operating hours, the motor’s grease should be replaced; use No. 3 base grease. If the motor has been stored unused for an extended period, before restarting it, inspect the bearings for adequate grease and replenish or replace it as necessary. The amount of grease to be filled should equal two-thirds of the bearing housing volume.
3. During motor operation, if the bearing temperature is found to be excessively high or the grease has deteriorated, the grease should be replaced promptly. The normal operating temperature of the bearing shall not exceed 95°C.
4. If the motor is to remain idle for an extended period, it should be stored in a clean, cool, and dry environment.
5. If the motor has been stored unused for an extended period, its insulation resistance should be measured before reuse; the value must not be less than 0.5 MΩ. If it falls below 0.5 MΩ, the motor must be dried, with the winding temperature not exceeding 121°C during the drying process.
II. Transmission Box
1. Before use, the gearbox shall be filled with lubricating oil; the recommended grade is medium‑pressure gear oil or another gear oil of similar viscosity. The oil level must reach the mark indicated on the oil dipstick. Note: Operation without lubricating oil is strictly prohibited.
2. Gearbox operating ambient temperature: 1–35°C. When the temperature exceeds this range, a lubrication heating or cooling system must be installed.
3. After the first 300–600 hours of operation, replace the lubricating oil; thereafter, change the oil every 4,000 hours. When performing the oil change, stop the gearbox and, while the oil is still warm, drain it completely. Rinse the gearbox thoroughly with lubricant of the same grade, then refill with the specified amount of new lubricant.
4. If the equipment is left idle for an extended period, it should be run without a load for a while upon resumption of use; only after the bearings have been thoroughly lubricated may it be operated under load. Regularly inspect all connection points and periodically check the condition of the gears for wear, addressing any issues promptly.
5. During operation, if any abnormal noise, vibration, or high temperature is detected, stop the machine immediately for inspection and resume use only after the fault has been rectified.
III. Instructions for Removing the Screw Rod
1. Before removing the screw, first dismantle the extruder die and ensure sufficient working space; prior to removal, empty as much material as possible from the screw.
2. The screw should be removed when the main machine is maintained at its normal process temperature. During disassembly, ensure adequate personal protection to prevent burns. Take care to protect the screw and avoid any damage to it.
Related products
Feedback
Shuangda
Hebei Shuangda Rubber Machinery Co., Ltd.
Tel:400-0319-386
Landline:+86-319-6017632
Email:shuangdaxiangsu@126.com
Official website:www.shuangdajx.com
Addr:Liyuantun Industrial Zone, Weixian County, Xingtai City, Hebei Province
Copyright © 2022 Hebei Shuangda Rubber Machinery Co., Ltd.